The Kano Electricity Distribution Company (KEDCO) has apologized to customers over epileptic power supply in Kano, Kastina, Jigawa states.
The Head, Corporate Communication department of the company, Alhaji Sani Bala Sani, gave update on power situation in a statement released to journalists .
According to him, KEDCO was informed by the Transmission Company of Nigeria, (TCN), that work is still ongoing on the lines and expected to be completed today (Sunday).
He recalled that Shiroro-Kaduna 330KV transmission lines 1 & 2 being its main sources of supply had been out on fault since 26th April 2023 and 11th June 2023 respectively, resulting in its franchise area being fed alternatively on the Jos 330KV transmission line.
“Consequently, this has been responsible for low megawatts allocation of an average of 60MW against approved 300MW.
“While appealing for your understanding and patience, we sincerely regret all inconveniences caused,” he added.