The Nigeria Government has said the erratic power supply currently being experienced in Abuja and other parts of the country was caused by the low water levels in the hydro dams.
Minister of Power Abubakar Aliyu said this on Thursday during the weekly ministerial briefing organized by the Presidential Communications Team, held at the Presidential Villa Abuja.
“With the reduction in hydro water in the dams during the dry season, the need for the additional load to be taken up by our gas plants and the challenges we are having in the repairs currently being carried on some of the generators are all responsible for the load shedding and power outages we are experiencing,” he said.
Aliyu, who spoke on various initiatives under the Ministry, including Presidential Power Initiatives (PPI) being driven by Siemens, said the government is doing everything to ensure an optimum supply of gas to ensure quick restoration of power.
National metering programme
The minister said the metering gaps are being reduced across the country with the rollout of one million meters for the first phase of the initiative while awaiting four million others under the second phase.
“Currently, close to one million meters have been rolled out under the first phase and accelerated procurement is ongoing for the second phase of four million meters with a critical focus on local manufacturers. This is aimed at providing jobs through the programme.
“The first phase generated 10, 000 jobs in installation and assembly. We anticipate that the second phase contract will be awarded by the end of the second quarter of this year. There will be a third phase that will provide additional two million meters, funded through the World Bank,” he said.
The Minister disclosed that government aims to provide meters for all households and eliminate the metering gap being experienced as well as jettison estimated billing.
He however cautioned distribution companies (DISCOS) that are involved in selling meters to desist from such acts as meter procurement is free.
Aliyu explained that the government is expediting action on the proposed installation of 10 power transformers with additional 10 mobile substations for massive improvement of electricity supply nationwide.
Challenges
The Power Minister said the issue of the right of way was stalling power projects despite the fact that findings are already on the ground.
He said: “We are engaging with the state governors through the Nigerian Governors Forum to drive a holistic solution to these lingering issues. Some examples of critical projects held up by right of way are Benin to Oshgbo which I’ve mentioned 330 KV line which is 250 kilometres, Ikot Ekepene to Ikot Abasi also 330 KV line 68 kilometre and the Kano-Katsina 330 KV line 180 Kilometer.”
He noted that the attention the power sector is receiving under the Muhammadu Buhari led administration is unprecedented.
“Since the inception of the present government under President Buhari in 2015, it has turned its attention to our infrastructure and the attention this government is giving in my own view is unprecedented. If we narrow that to the Power sector, it is also receiving such attention.
“The enormity of the decay in the sector is what we are battling with to ensure we overcome challenges associated with electricity delivery in the country,” he said. (VON)
The Chief Executive Officer of Air Peace, Allen Onyema, has been hit with new charges…
Contrary to reports in a section of the media that the Nigerian Upstream Petroleum…
Tajudeen Suleiman It was a pleasant shock for me to read the National Bureau of…
A member of the House of Representatives, representing Isiala Mbano / Onuimo / Okigwe…
Leading financial institution in Nigeria, Fidelity Bank Plc, has assured its customers of unwavering…
Fidelity Bank Plc complies with the highest corporate governance standards as the leading commercial…
This website uses cookies.